Courtland Creek Restoration Project

Status:
In Process

About

The City is designing a creek restoration project that will be built in three sections of Courtland Creek Park. The Courtland Creek Restoration Project (Project), an Oakland Measure DD Initiative, will protect, enhance, and restore approximately 950 feet of open creek channel.

The Project will improve creek habitat and water quality, reduce trash accumulation and illegal dumping, repair steep and eroding creek banks, enhance climate change resilience and park appearance, and serve the community as an educational and recreational resource. Accessible seating, gathering places, and a creek-viewing overlook will also be provided.

Project partners include the Oakland Parks and Recreation Foundation (OPRF), the Friends of Courtland Creek, and local schools. This Project is fully funded. Grants have been received from the California Department of Water Resources ($1 million), the United States Environmental Protection Agency, San Francisco Bay Water Quality Improvement Fund ($1.5 million), and Caltrans Clean California Local Grant Program ($2.03 million).

The Project consultant has completed Project designs, which staff and OPRF presented to community members at Community Meetings on May 12th and May 14th, 2022 in accordance with the Project’s equity-focused public engagement plan. Please see the documents below for the Courtland Creek Community Meeting invite for May 2022.

Community Meeting Presentations and a Summary of the meetings held in July 2021 and May 2022 can also be found under the documents below. The current anticipated Project construction date is January 2023 for tree removal work and May 2023 for the remainder of the creek restoration project.

Documents

Map

Map of Project: Courtland Creek Restoration Project
Map of Project: Courtland Creek Restoration Project

Courtland Creek Park

Timeline

Phase I: Planning, Preliminary Design, Meetings
August 2019 - July 2021, Public Meetings in July
Phase II: Advanced Design
August 2021 - August 2022
Public Meetings
May 12 and 14, 2022
Phase III: Construction Bid & Contractor Selection
August 2022 - March 2023
Phase IV: Construction
January 2023 and May 2023 - October 2023
Phase V: Education, Recreation & Stewardship
October 2023 and beyond

Partners

Skyline color circle white background 2814px
Skyline color landscape clear background 3904px
Epa seal large trim
NEW DWR LOGO 3600pixels
DD logo 214x236
Clean CA

Contact

Email

watersheds@oaklandca.gov

Phone Numbers

Phone: 510 238-6191